Wyndwood pipeline expansion project approved by National Energy Board

Wyndwood

Wyndwood pipeline expansion

 Project is a loop of Westcoast’s existing Fort St. John Mainline

The National Energy Board (NEB) approved a proposal from Westcoast Energy Inc., doing business as Spectra Energy Transmission, to build and operate the 27-kilometre-long Wyndwood Pipeline Expansion Project, according to a press release.

The NEB announced its decision in a letter, released today, and expects to issue detailed reasons on or before Sept. 28. The estimated cost for the project is $170.3 million.

The NEB attached 32 conditions to its approval, including the requirement to develop a Landowner-Specific Monitoring Plan and Consultation Update and a number of conditions related to minimizing disturbances within caribou ranges and accelerating the restoration of caribou habitat.

 

Markham Hislop, publisher, North American Energy News.

Subscribe now if you value old-school journalism in a post-fact, fake news online media world. Subscribe now if reliable, balanced, objective energy reporting – the kind practised by Markham Hislop and his news team – appeals to you. Subscribe for as little as $50 per year.

Westcoast submitted its application on Oct. 21, 2016 under section 58 of the National Energy Board Act. In general, these types of applications do not require a public hearing.

However, given the high level of public interest in this project, the NEB decided to hold a hearing in order to consider the input of those who could be directly affected or who have expertise to share.

Oral hearings were held on April 5, 2017 in Calgary and June 6 – 7, 2017 in Chetwynd, BC.

The NEB also gathered input through written comments, questions and evidence.

After considering all the evidence, the NEB found that the project was in the Canadian public interest.

This project is a loop of Westcoast’s existing Fort St. John Mainline.